April 22nd - Downtown Lakeland Paving Project Update

LAKELAND, FL (April 22, 2011) - Much of the downtown area paving project will be completed before close of business day.  Crews will be working on Saturday from 4 p.m. – 9 p.m. with the focus on milling the curb edges along Main Street between Tennessee and Kentucky Avenue.  There will be additional milling during the same time period along the curb lines of Lemon and Orange Streets.

 

Paving will resume on Monday, April 25th at approximately 6:30 a.m.  Paving will start on Main Street at Florida Avenue working east block by block.  As paving on Main Street is completed, the crews will move to Lemon Street and resume paving on Tuesday morning at 6:30 a.m. to finish Orange Street. 

 