Engineering's Capital Improvement Projects

North Lakeland Stormwater Improvements – Basin A - Completed

Parker Street 3-Lane Conversion - Completed

New Jersey Road Sidewalk from Crystal Lake Drive to Edgewood Drive - Design and construct sidewalk on the west side of New Jersey Road from Crystal Lake Drive to Edgewood Drive.

West Highland Street Sidewalk (Pinewood Avenue to Southern Avenue) - Design and construction of sidewalk on both sides of West Highland Street between Pinewood Avenue and western entrance of Kings Manor Mobile Home Park and on south side of West Highland Street between Kings Manor Mobile Home Park and Southern Avenue.

Hollingsworth Road Sidewalk - Design and easement acquisition in Fiscal Year 2014 and 2015 for sidewalk on the east side of Hollingsworth Road from Lake Hollingsworth Drive to Lakeland High School. Construction is currently planned for Fiscal Year 2016.

Three Parks Trail South - Design and construction of a muti-use asphalt trail extending the Buckingham Avenue Trail from Acrleton Street south along the edge of Cleveland Heights Golf Course and connecting to Cleveland heights Boulevard. This trail will serve as Three Parks Trail Segment 6 in the City's Master Plan study.

Three Parks Trail North - New multi-use asphalt trail from western end of Glendale Street at the Cleveland Heights Golf Course along the eastern and northern boundaries of the golf course and connecting to the existing Edgewood Drive Trail near Southington Avenue. Design in Fiscal Year 2014 funded by Transportation Fund and construction in Fiscal Year 2015 funded by a reimbursable grant through FDOT LAP agreement.

Bella Vista Trail - New multi-use asphalt trail on the south side of Bella Vista Street from Martin L King Bl. to US 98 N and on the north side from US 98 N to West Lake Parker Drive. Design in Fiscal Year 2013/2014 funded by CRA and construction in Fiscal Year 2015 funded by a reimbursable grant through an FDOT LAP agreement.

Olive Street Bike Lanes - Design and construction of bike lanes in conjunction with scheduled street resurfacing project. Design in Fiscal Year 2014 funded by Transportation Fund and construction in Fiscal Year 2015 funded by a reimbursable grant through an FDOT LAP agreement.

Sylvester Road Sidewalk - Design and construction of approximately 1,400 feet of sidewalk gaps on the north side of Sylvester Road from Fredricksburg Avenue to Bartow Road.

Robson Street Drainage System Enhancement - Piping the existing ditch on the north side of Robson Street from Baird Avenue to the Robson Street Bridge.

Robson Street Sidewalk - Design and construction of sidewalk on the north side of Robson Street from Baird Avenue to the Robson Street Bridge in conjunction with the Robson Street Drainage System Enhancement project.

Brunnell Parkway Sidewalk - Design and construction of new sidewalk on the east side of Brunnell Parkway from Parker Street to Memorial Boulevard.