Current Construction Phase:
With the new water, sewer, and drainage systems installed and the new northbound lanes prepared, crews will begin connecting the new utilities and removing the old water and sewer lines on the west side of the roadway.
To safely complete this work, traffic will be shifted onto the new lanes on the east side of the roadway- first from north of E. Bella Vista Street to Griffin Road, starting July 9, and next from Parkview Place to E. Bella Vista Street in late July/early August 2026. Both northbound and southbound traffic will be traveling on the new lanes!
To safely complete this work, traffic will be shifted onto the new lanes on the east side of the roadway- first from north of E. Bella Vista Street to Griffin Road, starting July 9, and next from Parkview Place to E. Bella Vista Street in late July/early August 2026. Both northbound and southbound traffic will be traveling on the new lanes!
SR 33 (Lakeland Hills Boulevard) Improvement Project
- Start Date: October 7, 2024
- End Date: 2026 - TBD (Ongoing construction phases)
Major Points:
- Roadway Changes: Four travel lanes with curb and gutter from Parkview Place to north of Miami Street; 12-foot raised median; bi-directional left turn lane north of Miami Street to Granada Street.
- Safety Upgrades: New mid-block pedestrian crossings with Rectangular Rapid Flashing Beacon (RRFB) and Pedestrian Hybrid Beacon (PHB), 8-foot sidewalks, ADA-compliant ramps, LED traffic signals.
- Lighting: Street lighting added and upgraded at signalized intersections.
- Construction Impact: Lane closures, detours, and temporary side street closures; enhanced bus routes by Citrus Connection starting October 21, 2024.
Learn more about this project at https://www.swflroads.com/project/440444-1