WHO: Contractors working for the City of Lakeland
WHAT: Milling and paving projects
WHY: Roadway resurfacing part of preventative maintenance schedule
WHEN: Starting June 2, 2026
WHERE: Lake Hollingsworth Road, Martin L. King Jr Avenue and Tucker Street, South New York Avenue, Cheverly Drive (East and West), Canyon Lake Point and Kells Court
LAKELAND, FL – The City of Lakeland will begin milling and resurfacing several collector and residential streets as part of its roadway preventative maintenance program on Tuesday, June 2, 2026. The work will involve removing approximately 1.5 inches of existing asphalt (milling) and replacing it with 1.5 inches of new asphalt. This milling process is a standard practice that helps maintain consistent driveway and ADA ramp elevations, preventing the need for adjustments due to changes in pavement height. Below are the start and completion dates for each project. Please note that weather conditions and equipment issues may cause slight delays.
These projects will be carried out during daylight hours. Once work is completed each day, the roads will reopen to through traffic. However, drivers should expect delays throughout the duration of the projects. While the roads will remain open, motorists are encouraged to use alternate routes when possible. Each road will be reduced to one lane, with flaggers directing traffic around the milling and paving equipment convoy. With the exception of Lake Hollingsworth Road, this road will maintain southbound traffic flow throughout the project. And we will have intermittent detours of the northbound traffic, maintaining a flagging operation when possible. Any necessary detours will be clearly marked. City employees will distribute door hanger notices prior to work starting on each street.
Here's the list of the streets to be paved and associated dates:
Lake Hollingsworth Road from Bartow Road to the roundabout (June 2 – June 3, 2026)
Martin L. King Jr. Avenue & Tucker Street from 10TH Street to US 98 North (June 3 – June 5, 2026)
New York Avenue from Lenox Street to Palmetto Street (June 8 – June 11, 2026)
Cheverly Drive (east and west) (June 10 – June 12, 2026)
Canyon Lake Point from East Cheverly Drive to north end (June 14 – June 12, 2026)
Kells Court from Cheverly Drive East to end (June 11 – June 12, 2026)
Contact Troy Williams, Pavement Coordinator, at (863) 834-3315 with questions and continue to check (863) 834-ROAD (7623) for updated information. Please visit http://www.lakelandgov.net for updated information. Follow the City of Lakeland Facebook page at http://www.facebook.com/Lakelandgov.